<-- Twitter Summary card images must be at least 120x120px -->
 
 

Medupi’s Unit 5 synchronised to the national grid

 
News : 14 Sep 2016 86 Viewed By Press Release 0

LEPHALALE – Medupi power station’s unit five was synchronised to the national power grid on Thursday, becoming the second of the power station’s six units to come on stream.

Synchronisation is achieved when the generator in the unit is connected into the power grid so that it is aligned with all other generators on the national grid. It then starts to generate and deliver electricity into the grid over several months. Unit five’s synchronization marks a key milestone towards the full commercial operation of the unit ahead of its scheduled commercial operation in March 2018.

Once completed, Medupi will be the fourth largest coal-fired power plant, and the largest dry-cooled power station in the world. It will consist of six units with an installed capacity of 4 800MW. The planned operational life of the power station is 50 years.

The Medupi power station uses direct dry-cooling systems due to the water scarcity in the Lephalale area. Dry-cooling systems use air instead of water to cool the steam exiting a turbine. The power plant incorporates super critical technology which is able to operate at higher temperatures than Eskom’s earlier generation of boilers and turbines. Importantly, the technology enables the power plant to operate with greater efficiency, resulting in better use of natural resources such as water and coal, and will have improved environmental performance.

 “Medupi Unit 5 synchronisation is a clear indication that we are on track on delivering the entire New Build programme to the country. This milestone further strengthens our position that load shedding is becoming a thing of the past. I am thrilled by this achievement. Eskom has turned the corner,” said Eskom Group Chief Executive Brian Molefe.

Eskom chairperson Dr Baldwin Ngubane remarked that the achievement of Medupi’s unit five synchronisation is proof that Eskom is in good hands under the leadership of Brian Molefe and his executive team. “We commend the team for their dedication and commitment in working tirelessly to ensure that Unit 5 synchronisation is achieved ahead of schedule. This is a remarkable achievement.”

 

 

 

 
 

 

0 Comments

To leave a comment you need to login / register first
 
 
 
 

Facebook Twitter Youtube